How do you price mobilisation costs in a UK tender?

A site table with a project plan, calculator, helmet, and green folder overlooks an excavator and materials.
,

How do you price mobilisation costs in a UK tender?

How to work out what it costs to get a contract ready to start, how the buyer’s payment rules and caps affect it, and how to fund the weeks before your first invoice is paid.

How do you price mobilisation costs in a UK tender?

Work out every task that has to happen before delivery starts, cost each one from real quantities, staff time and quotes, then fit the total into the buyer’s pricing schedule and payment rules. Your figure should match your mobilisation plan and leave you able to fund the gap until the first payment arrives.

Mobilisation costs are the costs of getting ready to deliver a contract. On a works contract that means moving plant, people and materials to site and setting up temporary facilities. On a service contract it’s more likely to be recruitment, induction, premises and setting up systems. You’ll also see it spelled “mobilization” in US guidance, and the meaning is the same.

It’s worth sorting this out early. Pricing is often the last part of a bid to settle, and when mobilisation gets left to finance in the final few days, it tends to be either missed or counted twice.

What will the buyer pay for, and when?

Read the pricing schedule, the specification and the draft contract together, because the label beside a spreadsheet cell rarely tells you the whole commercial position.

Does the tender allow a separate mobilisation charge?

Some public contracts list mobilisation as its own lump-sum item, paid early in the contract. Others expect you to recover set-up costs through your monthly or unit charges. Check whether a separate charge is allowed, what it’s meant to cover and what has to happen before you can invoice it, such as an accepted mobilisation plan or a readiness milestone.

The Cabinet Office’s Construction Playbook links the payment approach to how much risk and uncertainty a contract carries, and that thinking is useful well beyond construction. There’s no standard UK mobilisation percentage, so the tender documents are the only place that can tell you what’s allowed.

What about the caps and percentages you see online?

Plenty of online guides quote a 5% or 10% mobilisation cap, and many of them are describing US federal rules. A percentage like that only applies to your bid if the tender documents in front of you set it. If they do, check whether it limits what you can charge for mobilisation, how much you can be paid early, or both.

How do you build the estimate around delivery?

Your mobilisation plan is the starting point. Every activity in it should have a resource, a cost and a named owner, so the price and the plan tell the same story. Our guide to building a mobilisation timeline helps you map those activities, who owns them and what depends on what.

What drives the cost on works contracts?

On works and equipment-heavy contracts, the kit you need often drives the cost more than the size of the job. A crane, specialist plant or temporary facilities each need their own quote for transport, set-up and removal. Separate the one-off delivery and set-up charges from ongoing hire and put each in the right pricing line. Check the quotes against the programme and site access too, because a delayed start can stretch hire periods and labour costs.

What drives the cost on service contracts?

On service contracts the big costs are usually people and time. Recruiting staff, inducting and training them, setting up IT systems and preparing premises all happen before the first service payment. Include the management time it takes to run mobilisation, and any period where the old and new arrangements overlap. Where TUPE applies, build your staffing assumptions from the employee information the buyer gives you, and take employment advice on anything unclear.

How do you calculate each mobilisation cost?

Build the estimate in a working file that shows how you reached every number, so someone else can follow it later. The government’s cost estimating guidance is a useful reference for recording assumptions and handling uncertainty.

Begin by fixing the mobilisation period, from the first activity to the service start date, and note anything that carries on after go-live. Then measure the resources against your delivery programme, such as staff hours, plant movements and equipment. Apply rates you can evidence, using supplier quotes and fully loaded staff costs that include employer contributions.

Next, allocate a fair share of management and central support costs on a basis you’ve written down, and check it against the wider contract budget. Then price the risks you’ve identified, recording each one and what it could cost, before you apply your margin. Keep contingency visible in your internal model, even if the buyer’s schedule has no line for it.

Ask finance to check the VAT position on each cost as well, because being a charity or social enterprise doesn’t decide on its own whether VAT can be recovered. Keep the cost of winning the bid separate from the cost of mobilising the contract too. Our bid cost calculator covers what you spend before award.

How does a mobilisation cap work in practice?

A cap can limit the amount you charge for mobilisation, the amount you can be paid early, or both. Read the clause carefully, because “mobilisation” can mean an activity, a cost or a payment stage, depending on who wrote it.

What does a real breakdown look like?

The High Court judgment in Birse Construction Ltd v McCormick (U.K.) Ltd records a contract price of £4,003,487, excluding VAT. The site preliminaries, meaning the costs that support delivery on site, were broken down like this.

Preliminaries itemRecorded amount
Mobilisation£204,463
Site establishment£261,300
Demobilisation£2,500
Total£468,263

These figures come from one contract, so treat them as an illustration. They show why mobilisation, site set-up and demobilisation are worth pricing as separate items.

How do you check whether you’re over a cap?

Say a tender set a 5% cap on mobilisation, measured against the contract price. On that contract, 5% of £4,003,487 is £200,174.35, so the recorded mobilisation figure of £204,463 would sit £4,288.65 over the limit. The example is there to show the method, and it doesn’t mean the Birse contract had a cap like this.

On a live tender, check whether the cap is measured against a price with or without VAT, and over which period. If the cap only controls early payment, you may be able to recover the rest later in the contract. If it limits the charge itself, the shortfall has to come out of your margin. Raise anything unclear through a clarification question before you submit, because moving the excess into another pricing line can lead to double counting or an unbalanced price.

How much cash do you need before the first payment?

A profitable contract can still need a lot of working capital. Recruitment fees and payroll go out on their own timetable, and the contract may not let you send the first invoice until a milestone has been signed off.

Build a weekly or monthly cash flow forecast covering mobilisation and the first months of delivery, showing when each cost leaves your account, when you’re allowed to invoice and when payment should arrive. For contracts under the Procurement Act 2023, the government’s guidance on payment requirements explains the 30-day payment term written into relevant public contracts. That clock starts when a valid invoice is received, so it won’t help if the contract doesn’t let you invoice until later. Our post on what to check in public contract payment terms goes through this in more detail.

Find the lowest point in your cumulative cash position, because that’s the funding you need. Then test what happens if the first payment is late, mobilisation takes longer or the outgoing supplier hands over information late. If reserves will cover the gap, make that visible to whoever signs off the bid, so they approve the cash commitment alongside the margin.

Should you price demobilisation as well?

Yes, it’s worth pricing at the same time. Demobilisation is the cost of winding down at the end of the contract, and it’s easy to forget when everyone is focused on the start. Estimating it alongside mobilisation means the final months have a budget.

On works contracts it can include removing plant and temporary facilities and leaving the site in the condition the contract requires. On service contracts it might mean transferring records, closing down systems and supporting staff through a handover to the next supplier. The contract’s exit and handover clauses tell you what you’re responsible for.

Look out for any risk of pausing and restarting partway through as well. A second mobilisation can mean another round of transport, recalling staff and lost time, and the contract decides whether you carry that cost or can claim it back. Price what you can foresee, and write down the assumptions behind the rest.

How do you explain the price to evaluators?

Your pricing narrative should help the evaluator see how the resources you’ve priced support what you’ve promised in the quality answers. Use the buyer’s terms and point to the main cost drivers. If system testing needs paid staff time, show where that time sits. If an equipment delivery sets your start date, link the quote to the programme.

Do your price and quality answers match?

Check the staffing in your price against the mobilisation timetable in your quality answer. A named mobilisation lead working full time for six weeks needs six weeks of cost behind them. The same goes for extra training sessions, stakeholder meetings and anything else the quality team has offered with enthusiasm.

Melissa’s insider tip

When I’m evaluating, I read the price and the mobilisation plan side by side. A plan with a dedicated set-up team and a price with nothing in it to pay for them is one of the quickest ways to lose my confidence in a bid.

Which pricing mistakes come up most?

The most common one is the same cost appearing in two or three places, such as a mobilisation line, the site preliminaries and an overhead allocation. Reconcile the whole pricing workbook so each cost goes in once. Front-loading is another, where early payments are bigger than the work done in those first weeks would justify. Buyers look for it, so keep early charges tied to their scope.

If you need to make assumptions, state them precisely and follow the tender’s rules, as some tenders don’t allow qualifications at all. Before sign-off, check that every mobilisation commitment has an owner and a cost, the pricing follows the buyer’s definitions, the forecast covers the weeks before the first payment, and finance and delivery have agreed the same figures. For a last look at the written answer, The Evaluator’s Eye Test gives you five free checks to run before it goes in.

Questions about mobilisation costs

Tap a question to see the answer.

A mobilisation fee is a charge for getting ready to deliver the contract, such as setting up staff, systems or equipment. The tender documents decide whether you can show it as a separate item or need to recover it through your ongoing charges.

Not necessarily. Even where your price includes a mobilisation lump sum, the contract may only let you invoice it once a plan is accepted or a milestone is met. Check the payment trigger and plan your cash flow around it.

No. The cost depends on the resources, equipment and preparation time the contract needs. Comparing your figure with the contract value can be a useful sense check, and the number itself has to come from your own estimate.

A cap limits how much the buyer pays before delivery has started, and it discourages front-loading. Check whether the cap limits the price, the early payment or both, because each has a different effect on your margin and cash flow.

Give your contract a funded start

A credible mobilisation price comes from an agreed delivery plan and a calculation someone else can follow, backed by a cash forecast that shows you can carry the first few months.

At Bidsmithery™, we help teams look at their bids through an evaluator’s eyes while they keep ownership of the work. If you’d like a second pair of eyes before your next deadline, book a fit check call.

How we can help

Bid review retainer

Expert eyes on your drafts before you press submit, whenever a tender lands.

See how it works →

Bid training

Build the skill inside your team, so every bid gets a little easier.

See how it works →

Free guides and tools

Practical freebies from the evaluator’s side, ready to use on your next bid.

Browse the freebies →

Not sure what you need?

Grab a cuppa and let’s talk bids. Tell us what you’re working on and we’ll point you to whatever will make the biggest difference.

Melissa Howard, founder of Bidsmithery

Meet the author

Melissa Howard knows what evaluators look for, because she’s been one. She founded Bidsmithery™ after 15 years writing, managing and scoring bids across more than 10 sectors, and in the past three years her clients have won more than £103m in contracts.

The Bidsmithery™ secret sauce is simple: your team writes the bid, and Melissa reviews it before you submit, showing you where you’re losing marks and how to fix them. She also trains teams, so every bid gets easier.

Bidsmithery
Bid tips with your Friday cuppa

Practical tips from the evaluator’s side of the table, every Friday. Unsubscribe any time.

You may also like....