When can buyers agree a public contract extension?

Three smiling colleagues reviewing charts at a meeting table, discussing a public contract extension

When can buyers agree a public contract extension?

What has to be true before a UK buyer can extend a public contract, from the lawful grounds to the 10% test and the notices.

When can UK buyers extend public contracts?

A UK buyer can agree a public contract extension without retendering when the change fits a permitted modification ground under the Procurement Act 2023. An extension option written into the original contract documents may qualify, as long as the buyer uses it within its terms and limits.

With the end date getting closer and a service that can’t stop, the buyer needs a lawful ground, evidence to back it up, and the right approvals and notices in place before the contract runs out. If you’re the supplier, this often arrives as a friendly call asking whether you could carry on for another six months. This guide walks through what has to be true before anyone says yes, so both sides know where they stand.

The Cabinet Office’s contract modifications guidance identifies ten grounds in total, including unforeseeable circumstances and a known risk that has come to pass. Whichever ground the buyer relies on, it has to check the conditions, calculate the permitted change and meet any publication duties.

Which procurement rules apply to the contract?

When did the procurement begin?

The first job is working out which rules govern the contract. The Procurement Act 2023 regime began on 24th February 2025 and generally covers procurements started from that date in England, Wales and Northern Ireland.

Earlier procurements and the contracts that came out of them generally stay under the previous legislation. For many ordinary public contracts, that means regulation 72 of the Public Contracts Regulations 2015 governs modifications. The date the procurement started is what counts, so a contract signed after the Act began can still sit under the old regime.

Above the relevant threshold, buyers generally need to compete a public contract unless a lawful exception or another compliant route applies. However well the incumbent supplier has performed, good performance on its own gives the buyer no ground for an extension.

Does the sector or nation change things?

Devolved Scottish procurement follows separate legislation. Certain healthcare services in England fall under the Provider Selection Regime, while equipment purchases may follow the Procurement Act.

Smaller contracts need attention too. A modification can turn a below-threshold contract into a “convertible contract” by taking its value into public contract territory, and the modification rules and notice requirements then apply. Our guide to bidding for below-threshold contracts covers the separate considerations for smaller opportunities.

Which grounds allow a public contract extension?

Can the buyer use an extension option already in the contract?

Start with the signed contract and the original procurement documents. A well-drafted extension clause says what the buyer can extend and the conditions for doing so.

The “provided for” ground, carried over from the old regulations, needs the change to have been unambiguously provided for in the contract and in the original tender or transparency notice. It must also keep the overall nature of the contract the same.

An advertised extension option gives the buyer a clear starting point. The buyer still has to follow the option’s conditions, including any deadline for exercising it, and the two parties agreeing between themselves can’t override procurement law.

What about the other grounds carried over from the old rules?

Schedule 8 to the Procurement Act 2023 sets out the modification provisions. The Cabinet Office identifies three further grounds carried forward from the previous regulations, and each one can allow a change when its conditions are met.

Unforeseeable circumstances can justify a necessary change where the buyer could not reasonably have seen them coming. The change must keep the contract’s overall nature, and the increase in estimated value is capped at 50%, with utilities contracts as the exception.

Additional goods, services or works can qualify where the statutory conditions make switching supplier impracticable. The buyer needs evidence of the technical or economic difficulties, and of the inconvenience or duplicated costs a switch would cause. The same 50% cap applies outside utilities contracts.

A change of supplier following a merger, acquisition or other corporate restructuring may also qualify. That ground covers the change of supplier, so any extension that comes with it needs its own lawful basis. A supplier wanting another year, however understandable, meets none of these conditions.

Which new grounds did the Procurement Act add?

The Act adds a ground linked to situations that would justify a direct award under its urgency or protection of life provisions. The statutory conditions must be met, and a slipping procurement timetable won’t count as urgency on its own. The buyer has to explain the circumstances and why the proposed change meets those conditions.

A known risk can also qualify. The government’s known risk guide sets out the conditions. The risk must have been identified in the original tender notice or transparency notice, it must have been impossible to address in the contract as awarded, and it must later occur and prevent satisfactory performance.

The change must go no further than needed to deal with the problem, and the buyer must conclude that awarding a further contract would not serve the public interest. The increase in estimated value can’t exceed 50%, outside utilities contracts. Government guidance uses cyber attacks and reinforced autoclaved aerated concrete (RAAC) as examples. Keep the original notice and the records showing how the risk occurred and why the change was necessary, because an internal risk register on its own won’t meet the notice requirement.

Two further grounds apply only to qualifying defence authority contracts, covering technological developments and maintaining defence operational capabilities. Together with the retained grounds, non-substantial modifications and below-threshold modifications, they make up the ten.

How do you calculate the duration and value limits?

How does the 10% duration test work?

The Act’s modification provisions set out when a change counts as substantial. For the non-substantial route, the 10% limit is based on the maximum contract term provided for on award, which includes any extension options already written into the contract. Adding or removing more than 10% makes the change substantial. To test a proposed extension, compare its length with that maximum term.

Maximum term provided for on awardProposed additional periodDuration-test result
Four yearsFive monthsThis exceeds the 4.8-month limit.
Five yearsOne yearThis adds 20% and exceeds the limit.
Five years, comprising three years plus two optional yearsSix months beyond that maximumThis equals 10%, so it passes the duration test only.

The five-year example comes from Cabinet Office guidance, and the four-year result uses the same arithmetic, because 48 months multiplied by 10% equals 4.8 months.

Passing the duration test is only part of the picture. The change must also leave the scope of the contract, meaning the work it covers, materially the same, and it mustn’t materially shift the “economic balance” in the supplier’s favour. That’s the commercial bargain, including how the parties share financial benefits and risks, so even a short extension needs a careful look if it also changes pricing or reduces what the supplier has to do.

How do you work out the percentage change in value?

The Cabinet Office’s contract governance module explains the below-threshold modification route. The value increase or decrease must be no more than 10% for goods or services, or 15% for works, and the scope of the contract can’t change materially. Work out the percentage by dividing the value of the change by the relevant estimated value, then multiplying by 100.

Government guidance uses the estimated value immediately before the change. Some legal commentators have questioned that, because the Act doesn’t say exactly when to measure it. Record the figure you used and how you calculated it, and get procurement law advice where the answer turns on that point. This route isn’t available if another modification ground applies.

What is the aggregate financial ceiling?

The combined value of below-threshold modifications must stay below the relevant threshold for that type of contract. Older Cabinet Office guidance illustrates this using £139,688 for a goods contract, which is now out of date, so keep it out of your extension spreadsheet.

The government’s 2026 threshold update gives ordinary goods and services thresholds of £135,018 for central government and £207,720 for sub-central authorities, including VAT, from 1st January 2026. Other categories have different thresholds.

The figure that applies depends on the governing rules and the contract category, and the percentage cap and the aggregate ceiling both have to be met. The name can mislead here, because the below-threshold modification route is about the size of the change, so the original contract can be above threshold.

How do you record and publish the extension?

What should the extension record include?

Take the Cabinet Office’s five-year example. The buyer wants an extra year that the original documents didn’t provide for. That adds 20% to the duration, so the non-substantial route fails the term test and a different ground would be needed. If the buyer looks at the below-threshold route instead, the value change has to stay within the goods or services percentage cap, and the aggregate ceiling and scope condition also apply.

A good record of a public contract extension walks through the process in order. It names the governing procurement regime, confirms the contract is still in force and says which contracting authority is making the decision. It sets out the maximum term provided for on award, including the original extension options, then describes the proposed change and its effect on duration and value.

From there, the record assesses each relevant ground, including the below-threshold route where it’s available, and lists any earlier modifications so the limits can be checked properly. It finishes with the approvals and a check on whether the contract’s value, including the change, is more than £5 million and brings in the publication rules.

Write the agreed change into the right contractual document. Identify the parties and the contract reference, state the new end date and any financial changes, and deal clearly with any related amendments. Follow the contract’s variation procedure and get authorised signatures. Where the parties are using an existing option, follow that option’s notification requirements.

Keep the evidence with the record, along with a copy of any required notice. Explain in your own words why the chosen ground applies, because a pasted extract of legislation leaves that question unanswered.

What needs publishing before the change takes effect?

Section 75 on contract change notices requires the buyer to publish a notice before making a modification unless a statutory exception applies. The exceptions include some smaller changes, and the answer also depends on the contract category, so the modification ground alone won’t settle it. Some light touch and private utility contracts have different requirements.

Where a notice is required, it should identify the contract, describe the change, explain the legal justification and give the prescribed information about its effect on value and duration. A transparency notice for a direct award serves a different purpose and can’t stand in for a required contract change notice.

The Act’s voluntary standstill provisions let the buyer pause after publishing. If it chooses to, the standstill must last at least eight working days, and the buyer must wait until the stated period ends.

When does the modification itself need publishing?

The Cabinet Office’s detailed publication guidance explains a further duty for qualifying modifications when the contract’s value, including the change, is more than £5 million. Where the contract change notice requirement applies, the buyer must publish the modification, or the contract as modified, on the central digital platform.

So the publication check has two parts, the advance notice and any later publication of the documents. Publishing a notice won’t make an unlawful change lawful, so the decision record still needs to show a valid ground, and the parties still need to complete the contractual formalities.

What extension mistakes should buyers and suppliers avoid?

Good delivery evidence helps the commercial case for continuity, although the buyer still needs a modification ground to rely on. Suppliers should keep a clear line between a buyer saying it would like to continue and an approved extension. Committing staff or holding capacity before the formal decision can leave an awkward gap between your forecast and what’s been signed.

Melissa’s insider tip

If a buyer rings to ask whether you’d carry on for a few more months, it’s fine to ask which ground they’re using and when the notice will go out. It protects you both, and the answer often tells you whether you should be getting ready for the retender.

Buyers need to look at the whole change. Section 74(7) stops a permitted modification being bundled with a non-permitted one to achieve a change that wouldn’t otherwise be allowed, so a lawful extension can’t carry an unrelated expansion of services with it. Splitting a larger change into several small modifications to stay under the limits won’t work either, which is another reason to keep the modification history with the approval record.

The judgment in James Waste Management v Essex County Council is still useful when thinking about economic balance. It was decided under the previous regime, and its treatment of the commercial bargain shows why percentages alone can’t settle every assessment.

Finally, start early. An expired contract generally can’t be revived through an extension letter. Where a new procurement turns out to be necessary, suppliers can use the remaining time to prepare evidence and take part in pre-market engagement, within the buyer’s published arrangements.

It also helps to see the retender coming. BidBestie can show you UK public sector opportunities that are on their way, so you have more time to get ready.

Free for 7 days
Biddy, the BidBestie mascot, checking a tender with a magnifying glass

Find your next tender, and see what’s coming up

BidBestie shows you UK public sector opportunities without the jargon, including the ones on their way, so your team spends less time searching and more time on bids worth going for.

Start your free trial

Questions about extending public contracts

Tap a question to see the answer.

Usually not, as long as the option meets the provided for ground and the buyer follows the conditions in the contract. The original contract and notice need to support the option. Using it is still subject to the buyer’s own approvals and any publication requirements, so leave time for those before the end date.

Yes. The test uses the maximum term provided for on award, including any original extension options. Exercising an existing option is different from adding time beyond that maximum, so keep earlier changes in the assessment record, because they may affect which grounds are still available.

Yes. You can explain the operational case and share relevant evidence, such as service continuity risks. The contracting authority has to establish the legal basis and make its own decision, so raise it early enough for the buyer to assess it properly before expiry.

The buyer can’t make the change under these provisions. It will need to consider a fresh procurement or another route that is lawful in its own right. Concerns about continuity can shape the buyer’s planning, although they don’t remove the conditions that apply to whichever route it chooses.

Plan for the end of the contract early

A defensible public contract extension starts with the governing rules and the original contract. From there, the buyer needs a valid ground backed by calculations, evidence and the right notices, and suppliers get the clarity they need to plan staffing and their next bid.

At Bidsmithery™, we help teams assess opportunities and strengthen the bids they choose to pursue, so if a retender is on the horizon, it’s worth getting ready early.

How we can help

Bid review retainer

Expert eyes on your drafts before you press submit, whenever a tender lands.

See how it works →

Bid training

Build the skill inside your team, so every bid gets a little easier.

See how it works →

Free guides and tools

Practical freebies from the evaluator’s side, ready to use on your next bid.

Browse the freebies →

Not sure what you need?

Grab a cuppa and let’s talk bids. Tell us what you’re working on and we’ll point you to whatever will make the biggest difference.

Melissa Howard, founder of Bidsmithery

Meet the author

Melissa Howard knows what evaluators look for, because she’s been one. She founded Bidsmithery™ after 15 years writing, managing and scoring bids across more than 10 sectors, and in the past three years her clients have won more than £103m in contracts.

The Bidsmithery™ secret sauce is simple: your team writes the bid, and Melissa reviews it before you submit, showing you where you’re losing marks and how to fix them. She also trains teams, so every bid gets easier.

Bidsmithery
Bid tips with your Friday cuppa

Practical tips from the evaluator’s side of the table, every Friday. Unsubscribe any time.

You may also like....