What can buyers ask in post-tender clarifications?

What can buyers ask in post-tender clarifications?
What a buyer can ask once your tender is in, where negotiation is different, and how to answer without accidentally rewriting your bid.
What’s in this post
- What are post-tender clarifications
- What can buyers ask after tender submission
- Which UK procurement rules apply
- How do you answer a post-tender clarification
- How is post-tender negotiation different
- What happens when your tender price looks abnormally low
- What mistakes put your clarification response at risk
- FAQs
What are post-tender clarifications?
Post-tender clarifications are questions a buyer asks after the submission deadline to resolve ambiguity, unusual information or an obvious error in a tender. They can help explain the offer you made, but they mustn’t materially change it.
If one has landed in your inbox and you’re not sure whether you’re allowed to correct something, the safest place to start is explaining what you submitted, with references the evaluator can follow.
Buyers have to protect fairness between suppliers, so your reply needs to answer their question without turning into a replacement bid. That means knowing what they can ask, where negotiation works differently and how to keep your answer within the rules.
What can buyers ask after tender submission?
Post-tender clarifications can cover an unclear commitment, conflicting information, an unusual price or what looks like a clerical error. The point is to clear up uncertainty so the buyer can assess your submission fairly.
From the evaluator’s side, the test is straightforward: can I assess this against the published award criteria without helping the bidder improve it?
Questions that explain the existing bid
A request might ask you to show which submitted attachment supports a statement, walk through a pricing calculation or reconcile two bits of wording that don’t match. The buyer should tell you clearly what the uncertainty is. Answer that point directly and leave the rest of your bid as it was.
Different bidders can receive different questions. Equal treatment means applying consistent standards to comparable issues, so the questions you get may look nothing like a competitor’s.
Requests that risk changing the offer
Adding a stronger delivery method, filling in missing substantive evidence or offering a lower price can change the competition. A clarification explains the offer you’ve already made, and anything that alters it needs separate authority in the procedure. The table shows where that line usually falls.
| Request | Where the boundary usually sits |
|---|---|
| Explain a calculation | Show how the submitted figures work. |
| Resolve conflicting commitments | Explain the existing offer without picking a new, improved commitment. |
| Supply a missing substantive answer | Usually amounts to completing the bid after the deadline. |
Whatever the message is labelled, look at what the buyer is actually asking you to do.
Which UK procurement rules apply?
If the procurement started on or after 24th February 2025 in England, Wales or Northern Ireland, it will usually fall under the Procurement Act 2023. Anything that started before then generally carries on under the old regulations, so check which regime the tender documents name before you reply. Scotland has its own legislation and guidance, which I’ll mention where it differs.
Does the procedure change what the buyer can ask?
Yes. The Act gives buyers two competitive procedures: the open procedure and the competitive flexible procedure. In an open procedure there’s very little room to change anything once tenders are in. The government’s competitive flexible procedure guidance explains how buyers can design stages, including negotiation, into that route.
If a buyer wants a negotiation stage, it has to be built into the advertised procedure from the start. It can’t be bolted on once final tenders have arrived. Lower-value contracts often still go through a competition under the buyer’s own purchasing rules, and for private sector tenders the buyer’s rules and contract terms carry more weight. In both cases, following the agreed route and keeping a record of what you sent is good practice.
For questions before the deadline, our guide to asking tender clarification questions covers that earlier stage.
When must a buyer consider clarifying an error?
An obvious error can sometimes be put right, depending on the rules, but a buyer doesn’t have to rescue every incomplete or badly written answer. The Court of Appeal looked at this boundary in Working on Wellbeing Ltd, trading as Optima Health, v Secretary of State for Work and Pensions [2025] EWCA Civ 127.
The Optima v DWP decision works through three stages: whether an error or ambiguity is obvious and material, whether clarification should be sought, and what response is allowed. Optima had been excluded from the competition, so the stakes were high. The court’s view was that a buyer needs to consider clarification before deciding an apparent error justifies rejection.
The permitted response is still limited. A bidder can’t submit a new bid or make substantial amendments, although correcting an obvious error within those limits can be allowed. The case was decided under the previous regime, so don’t treat it as a general right to correct errors under the Procurement Act.
How do you answer a post-tender clarification?
Start from the version you submitted, because your latest working draft may contain changes the buyer has never seen. Then pin down exactly what needs explaining. In a small team, bring in the person who wrote the original answer and whoever approved the commercial commitment, because a confident sentence won’t help if delivery and finance disagree.
What should the response include?
Quote each of the buyer’s questions with its reference, and give the answer in your opening sentence. Point to the submitted page, attachment or pricing line that supports it, and explain the ambiguity or error without adding anything new to the offer.
If the buyer has asked you to correct something, set out the correction clearly along with its effect. Then have an authorised person approve the response before it goes.
Melissa’s insider tip
When I see “we meant” followed by a rewritten service promise, I know the bidder is trying to improve their answer. If your reply needs a new delivery model to make the original answer work, you’re probably changing the bid.
How should you send and record it?
Reply in writing, ideally through the e-tendering portal’s messaging service, and keep a record of the request, the deadline, the approved response, any attachments and the submission receipt. If the buyer calls, note what was discussed and confirm it through the written channel, so no commitment lives only in someone’s memory.
Evaluators need evidence they can assess against the published criteria. Our guide to what evaluators look for explains why clear, traceable answers matter before submission too.
How is post-tender negotiation different?
Post-tender negotiation (PTN) happens after formal tenders arrive and before award, and its purpose is to improve value for money by agreeing changes to an offer. Clarification only establishes what you offered, so any change to the offer itself needs a lawful basis in the procedure.
When is negotiation allowed?
Scottish guidance goes into the most detail here. Where PTN is permitted, it expects a realistic prospect of better value for money, senior approval and full records. Negotiation usually focuses on the one or two bidders with the strongest submissions under the published award criteria, and tends to cover things like payment terms, delivery dates, warranties and after-sales support.
If you’re bidding under a Procurement Act open procedure, none of this gives the buyer authority to renegotiate your offer.
What is a Dutch auction?
A Dutch auction is when a buyer uses the lowest tender to push other bidders into cutting their prices. Asking a leading bidder to undercut a rival’s disclosed price crosses that line. A permitted negotiation follows the published process and never exposes a competitor’s confidential offer.
If you’re involved in a negotiation, expect the buyer to keep a full record of why it happened, who approved it, every exchange and how any agreed change was assessed against the rules. An email saying “price agreed” won’t show the process was fair.
What happens when your tender price looks abnormally low?
A low price can come from efficient delivery, a sound technical solution or good sourcing. It can also raise fair questions about whether the supplier can deliver for that money.
Under the Procurement Act 2023, a buyer that thinks a tender is abnormally low has to give the supplier a reasonable opportunity to show it can perform the contract for that price before disregarding the tender. In Scotland, buyers must also ask for an explanation, and Scotland’s clarification guidance says a tender must be rejected where the low price comes from breaching environmental, social or employment law obligations.
Explain your cost base, including how you deliver the service, any technical solution, your sourcing arrangements and the efficiencies you rely on, and back it up with evidence. Saying “we’re confident we can deliver” leaves the cost question unanswered. The exercise tests whether the price you submitted is credible, so your explanation has to stand behind that figure as it is.
What mistakes put your clarification response at risk?
The most tempting mistake is treating a clarification as another chance to earn marks. Extra case studies, stronger promises and revised methods might look helpful from inside your team, but they can make the response impermissible.
Sending the whole bid again causes problems too, because it makes it harder to see what changed and whether the change was allowed. Don’t replace the pricing workbook unless the procedure clearly permits it. Explain the relevant calculation first, and keep a clerical correction separate from anything that looks like a new price.
A late addendum from the buyer only allows the changes its instructions describe. And avoid informal reassurance through an existing contact. If a request seems to want a substantive change, raise that concern through the proper channel before you respond.
Questions about post-tender clarifications
Tap a question to see the answer.
Keep your clarification response clear and within bounds
A clarification request can feel uncomfortable after your team has worked so hard to submit. The strongest replies are precise and traceable, with every explanation tied to the offer the buyer received.
Fewer ambiguities in the first place means fewer awkward questions later. The Evaluator’s Eye Test gives you five free checks to run on any answer before you submit, and at Bidsmithery™ we bring the evaluator’s view to your structure, evidence and scoring logic while your team keeps control of the bid.
How we can help
Bid review retainer
Expert eyes on your drafts before you press submit, whenever a tender lands.
Bid training
Build the skill inside your team, so every bid gets a little easier.
Free guides and tools
Practical freebies from the evaluator’s side, ready to use on your next bid.
Not sure what you need?
Grab a cuppa and let’s talk bids. Tell us what you’re working on and we’ll point you to whatever will make the biggest difference.

Meet the author
Melissa Howard knows what evaluators look for, because she’s been one. She founded Bidsmithery™ after 15 years writing, managing and scoring bids across more than 10 sectors, and in the past three years her clients have won more than £103m in contracts.
The Bidsmithery™ secret sauce is simple: your team writes the bid, and Melissa reviews it before you submit, showing you where you’re losing marks and how to fix them. She also trains teams, so every bid gets easier.
Got time for another brew?
Want to keep reading?
Here are a few more guides from the evaluator’s side of the table.
-

How do you price mobilisation costs in a UK tender?
Read the post →: How do you price mobilisation costs in a UK tender? -

What should you check in UK public contract payment terms?
Read the post →: What should you check in UK public contract payment terms? -

Where can you find UK public sector tenders worth bidding for?
Read the post →: Where can you find UK public sector tenders worth bidding for?